The mysterious case of the Fountain Square realty project
Shukti Sarma 31 January 2012

Builders and buyers are silent on all quarters about the irregularities

Fountain Square, A mega residential-cum-commercial luxury project on Relief Road, Oshiwara, Jogeshwari (W) is stuck after being served a show-cause notice by the Mumbai Metropolitan Region Development Authority (MMRDA) for constructing two unauthorised basements. However, neither the buyers nor the builders are ready to answer questions pertaining to the building.

Moneylife has documents accessed under Right to Information (RTI) which show that Fountain Square, with Shri Shubh Builders and Sonata Realty—which is part of Ionic Group at its helm, was served a show-cause and stop work notice by MMRDA on 4 October 2011 after a site visit by officers on 19 September 2011. The letter to Sonata Realty by MMRDA says, “It was found that you have started construction of two level basements of the said building without obtaining permission from MMRDA. Therefore, you are instructed to show cause in writing within seven days… you are instructed to immediately stop the work and restore the land to its condition, existing before the said development took place, failing which necessary actions will be initiated.”

The commencement certificate for the project, dated 27 August 2009, says, “MMRDA has approved the proposal up to plinth (level) only in respect to the proposed building with total permissible built up area of 10,427 sq metres on plot bearing CTS no 1C/3A (pt), S.No.41/1A(pt) of village Oshiwara allotted to Sonata Realty Pvt Ltd.” Area free of FSI components is 35,335 sq mts. Entry against ‘total permissible basement area’ is ‘NA’.

Spaceage Consultants was appointed as the architect of the project. An MMRDA document on issuing of commencement certificate, dated 25 August 2009, says that the building proposal is for ground floor+14 upper floors, and the height of the building was to be 63.45 mts. However, MMRDA granted that in future, that height can go up to 70 mts; and that the architects and the realtors are to give in writing that the height will not go beyond the limit.  

However, initial brochures show a building that has almost 40 storeys.  Surprisingly, a recent brochure of the same project, which is available online on Ionic Group’s website, says that the project is of 30 storeys. See http://ionic.in/fl/Fountain_bro_small.pdf

On 9 May 2011 Spaceage Consultants approached the MMRDA for getting all necessary clearances for incorporating a ‘welfare centre’ in the design. After scrutinising their application, MMRDA issued a ‘deficiency letter’, listing 68 points. The 15 June, 2011 letter said that according to the lease deed, the building could have only residential and shopping use.

However, it also showed that the builders/realtors have not submitted many necessary documents, including NOCs from the fire department, civil aviation department, tree authority, electrical supply authority, high-rise committee and have also not got clearances for sewage, storm-water drain and environment impact assessment.

The letter also shows that the documents submitted neither indicates plinth level, presence of overhead tanks, facilities for the physically handicapped, undertakings against misuse, etc. Various aspects of the building like the marginal open spaces, driveway widths, distance from recreational grounds, etc, do not conform to development control regulations.

No answers could be obtained either from the builders, or the architects. Emails and phone calls to Ionic Group, Shubh Builders, Spaceage Consultants and Sonata Realty asking details like the present status of the project, scheduled date of completion, status of bookings, etc, went unanswered.

Even the buyers/investors are silent about the matter. “We cannot risk complaining as the builders may harass us. Moreover, we have only paid a nominal amount via cheque. The rest was in cash. The builders can then just give us the small cheque amount and tell us to forget the unaccounted amount we have paid,” said a buyer. The buyers, who have booked at levels beyond the 30th floor, are also unwilling to talk.
 
On the internet, there are many forums and discussion threads where users have expressed their anxiety about their investment. However, most of these pages cannot be accessed now. The construction hasn’t progressed much on ground either.

Rumours are afloat that the builders have submitted fresh plans to the civic authorities after the show-cause notice, but it could not be confirmed. “We have issued a show-cause notice, and the matter will be looked into,” said an MMRDA official.

Comments
zaverirushabh96
5 years ago
I have too purchased a flat and still don't have any news about whats happening with case Please help me as i am facing huge financial difficulties.
Nilesh Solanki
10 years ago
I am also one of the allottee in Fountain Square. Please let me know if any further actions are taken
+919428824525
[email protected]
Bilal Shaikh
1 decade ago
Dear Ms.Sukhti,
Iam one of the allottee of the flat in this fountain square project and last year environment clearance of only 23 floors received but till date only retaining wall permission is received. we came to know via internet there are about 240 flat allotments + Various unknown number of commercials. Also, there are many allotments above up to 39 floors. Can you please help us in raising this issue. we have formed a considerable group of members on whatsapp and discussing next course of action. can we get details of all allottees by RTI to prepare a strong case. Best Regards, Bilal Shaikh
Gazala Shaikh
Replied to Bilal Shaikh comment 9 years ago
Hi Bilal, can you please include me in the whatsapp group. Gazala +91 9833771231
Amar Sehmi
Replied to Bilal Shaikh comment 10 years ago
Billal saheb,
MY phone number is 9619209853
Let us be in touch and see what we can do. The work has started, though and developers claims that after all problems he faced he has necessary permissions in hand. Let us see what we can do as a group to expedite this matter. Please call me or whatsapp me
Farhana Pagarkar Chhapra
Replied to Bilal Shaikh comment 10 years ago
I have invested too in this project.now since its stalled I'm really worried.can you plzz include me also in the wats app group .waiting for a reply
Amar Sehmi
Replied to Bilal Shaikh comment 1 decade ago
Dear All,
I am also one of the victims. Let's do something together to tackle this issue. I cna be contacted at [email protected]
Amar Sehmi
Replied to Bilal Shaikh comment 1 decade ago
Dear Bilal,
I am also one of the victims of this fraudster developer. For the past 4 and half years nothing has happened from developers except false promises and wait wait wait. Let us get together and handle our case. I have paid substantially heavy booking amount with only allotment letter and no agreement as yet. I can be contacted on email: [email protected]